Active Stocks
Thu Mar 28 2024 15:59:33
  1. Tata Steel share price
  2. 155.90 2.00%
  1. ICICI Bank share price
  2. 1,095.75 1.08%
  1. HDFC Bank share price
  2. 1,448.20 0.52%
  1. ITC share price
  2. 428.55 0.13%
  1. Power Grid Corporation Of India share price
  2. 277.05 2.21%
Business News/ Industry / Bad loans may have been understated
BackBack

Bad loans may have been understated

Bad loans could far exceed published estimates if banks' exposure to completed power projects that are yet to start production is taken into account

Lack of fuel supplies and absence of power purchase agreements with state-run utilities have been blamed for stranded power plants. Photo: BloombergPremium
Lack of fuel supplies and absence of power purchase agreements with state-run utilities have been blamed for stranded power plants. Photo: Bloomberg

New Delhi: The amount of bad loans in India’s banking system may have been understated and could far exceed published estimates if banks’ exposure to completed power projects that are yet to start production is taken into account.

Lack of fuel supplies and absence of power purchase agreements with state-run utilities have been blamed for stranded power plants. Some project developers may not be commissioning constructed power plants because once they start production, they would have to start repaying their creditors.

For their part, banks and financial institutions that have funded these projects are not insisting that the developers set a date for the start of commercial operations. In the event that the developers default, the loans would be counted as non-performing assets (NPAs), requiring the lenders to make additional provisions, adding to the pile-up of bad loans and denting their profitability.

“Many projects which are otherwise technically ready are not declaring commercial operation date (COD) because of this lack of power purchase agreement and fuel supply agreement (FSA). It is typical of loan agreements that loan servicing starts after the project achieves COD," said Debasish Mishra, senior director of consulting at Deloitte Touche Tohmatsu India Pvt. Ltd.

Of 69,842 megawatts’ (MW) power projects stranded in the country at various stages of development, capacity totalling 45,634MW is stalled because of insufficient coal supply. Construction has been completed on projects with a capacity to generate around 28,000MW, but these haven’t been commissioned yet.

Forty listed Indian banks had gross NPAs of 2.52 trillion as of 30 June, up 21% from 2.08 trillion a year ago, as two years of sub-5% economic growth, tepid consumer demand and projects stuck because of delayed government approvals and land acquisition crimped corporate cash flows, hurting their ability to repay loans.

Banks’ exposure to the capital-intensive power sector is estimated at 3 trillion, more than the total amount of gross NPAs in the banking system.

A top executive at India’s largest power sector lender said delaying commercial operations to avoid defaults was a common practice in the power sector.

“Deferring commercial operation date to postpone NPAs is an issue," this executive said on condition of anonymity. “However, the issue of fuel shortage is being addressed at the highest level in the government. The options include using imported coal, pooling of domestic coal prices and rationalizing coal linkages as a short-term measure. These loans will not be allowed to turn into NPAs."

Of India’s installed power generation capacity of 250,257MW, around 60%, or 149,178.39MW, is coal-based. Growth in the production of coal has been unable to match the demand for fuel in a country where the power sector consumes nearly 78% of the domestic output of the mineral.

“The fuel (coal) shortage situation plaguing the power sector raises concerns regarding asset quality issues of the banks, with an estimated exposure of close to 3 lakh crore to the power sector," said Amol Kotwal, director, energy and environment practice, South Asia, Middle East and North Africa, at consulting firm Frost and Sullivan.

“Currently about 28,000MW of coal-based power plants are...complete, (but) developers are delaying the plant commissioning since the loan repayment kicks in from the COD," Kotwal added.

Bankers say the COD is beyond the control of project developers.

“There can be multiple reasons why COD is missed or reworked. RBI (Reserve Bank of India) has given us a provision to change COD if there is a bonafide reason for the delay, which is not in control of the developer," said a senior public sector banker on conditions of anonymity.

While India’s power generation capacity grew by 60% over the last five years, coal production only grew by around 6%. The country mined 532 million tonnes (mt) in 2009-10, 533mt in 2010-11 and 540mt in 2011-12. Production was 557mt in 2012-13 and 564 mt in 2013-14.

“The banks and financial institutions who have extended loans to the fuel-starved coal based plants are not insisting on declaration of COD to start repayments since the developers could potentially default," Kotwal added.

This comes in the backdrop of several private project developers dressing up their accounts while approaching banks for funding and inflating capital expenditure to increase debt value, thereby reducing their equity contribution. Also, these developers placed equipment orders with manufacturers that quoted inflated order values and later transferred the balance back to the developers, Mint reported on 4 December 2012.

“Everyone is aware of this practice. The banks are not insisting on COD as it will increase their NPAs. Then the real banking crisis will unfold. The numbers are artificially suppressed till there is a revival in the sector," a Mumbai-based power sector analyst said on condition of anonymity. “They are hoping for a soft landing. Delaying COD adds to the project cost in the form of additional interest during construction."

A second public sector banker said: “Theoretically speaking, yes, it is possible for a developer to not announce COD, but in reality that is not how things work."

He added: “Banks are vigilant when it comes to power projects and their function. Where it is necessary, banks will not shy from tagging the project as a non-performing asset." This person didn’t want to be identified either.

A power ministry spokesperson didn’t respond to emailed queries.

Piyush Goyal, India’s minister in charge of power, coal, and new and renewable energy, referred to the problems besetting the power sector in Parliament earlier this month.

Many power plants in the country have neither coal nor a buyer for electricity, Goyal told the Rajya Sabha on 6 August. He went on to add that NPAs of banks were increasing as a result.

The government was earlier working on providing a lifeline to 8,000MW of gas-based power projects stuck due to want of fuel that involved repayment concessions, Mint reported on 20 January.

The proposed concessions to the developers included an extension of COD, and providing two to three years’ moratorium on repayment along with the waiver of penal interest.

Vishwanath Nair in Mumbai contributed to this story.

Unlock a world of Benefits! From insightful newsletters to real-time stock tracking, breaking news and a personalized newsfeed – it's all here, just a click away! Login Now!

ABOUT THE AUTHOR
Utpal Bhaskar
"Utpal Bhaskar leads Mint's policy and economy coverage. He is part of Mint’s launch team, which he joined as a staff writer in 2006. Widely cited by authors and think-tanks, he has reported extensively on the intersection of India’s policy, polity and corporate space.
Catch all the Industry News, Banking News and Updates on Live Mint. Download The Mint News App to get Daily Market Updates.
More Less
Published: 22 Aug 2014, 12:37 AM IST
Next Story footLogo
Recommended For You
Switch to the Mint app for fast and personalized news - Get App